Title: 500 kV Mantaro-Nueva Yanango-Carapongo Interconnection and Associated Substations
Language: English
Type: Document
Nature: Case Study
Published: September 19, 2017
Region: Latin America and Caribbean (LAC)
Country: Peru
Sector: Energy and Power
Keywords: PPPs by Topic *, Asset Recycling **, Peru
Document Link(s):
Document Summary:
Case Study on Innovative Financing in Peru
Document Details:
The project allows the reinforcement of the transmission system in the central zone of the country, as well as the evacuation of surplus generation from the Mantaro zone towards Lima, foreseen in the new generation projects that will start operations in that area.
The project company signed the concession contract with the Peruvian State on September 19, 2017. The contract expires after 30 years from the date the service becomes operational.
Updated: