Assessing Value for Money of the PPP

Photo Credit: Image by Pixabay
A key objective of governments in implementing PPPs in infrastructure is to achieve value for money (VFM). Value for money means achieving the optimal combination of benefits and costs in delivering services users want. Many PPP programs require an assessment of whether a PPP is likely to offer better value for the public than traditional public procurement—often called value for money analysis. A VFM analysis can be done for a specific PPP project, and at a program level, for projects with common characteristics. For example, the United Kingdom Treasury's manual on assessing value for money (UK 2011b) described how value for money should be assessed at both the program and project levels (that methodology was later considered biased and recalled by government). VFM analysis typically involves a combination of qualitative and quantitative approaches. Qualitative VFM analysis consists of sense-checking the rationale for using a PPP. This involves asking whether a proposed project is of a type likely to be suitable for private financing, and whether the conditions are in place for the PPP to achieve value for money—for example, that the PPP has been structured well, and that competitive tension is expected during the bidding process. This often takes place at a relatively early stage of PPP development—as such, qualitative VFM analysis may constitute part of the PPP screening described in Screening for PPP Potential. Some PPP programs also require quantitative assessment of value for money. This typically involves comparing the chosen PPP option against a Public Sector Comparator (or PSC)—that is, what the project costs would look like if delivered through traditional procurement. This comparison can be made in different ways. The most common is to compare the fiscal cost under the two options—comparing the risk-adjusted cost to government of procuring the same project through traditional procurement, to the expected cost to government of the PPP (pre-procurement) or the actual PPP bids (post-procurement). An alternative is to compare the two options with an economic cost-benefit basis—that is, to quantitatively weigh the expected benefits of a PPP over traditional procurement against its additional costs. Value for money analysis—particularly using quantitative public sector comparator methodologies—has been widely debated. Some question the value and relevance of a PSC approach, which can appear to be more scientific than is the case, potentially misleading decision-makers; or conversely, may simply come too late in the process to be a genuine input to decision-making. A World Bank report on Value for Money (WB 2013a) analysis presents evidence on practices from several countries, and on trends regarding the scope of value for money analysis and the relative advantages of quantitative and qualitative approaches. For more discussion on approaches to assessing value for money, and their relative advantages and disadvantages, see also: The remainder of this section briefly describes and provides further resources for readers on qualitative and quantitative value for money assessment methodologies. Qualitative VFM analysis involves sense-checking the rationale for using PPP as a delivery mechanism—that is, asking whether a proposed project is of a type likely to be suitable for private financing; as well as whether the conditions that are necessary to achieve value for money are in place, as described in Farquharson et al, (Farquharson et al. 2011, 42–43). This often takes place at a relatively early stage of PPP development—as such, qualitative VFM analysis may overlap with the PPP Screening process described in Screening for PPP Potential above—but may be repeated throughout the project development process. Some jurisdictions have clearly-defined criteria for this analysis. For example: The EPEC Guide to Guidance also includes a list of key conditions that should be met to have a higher probability of achieving value for money (EPEC 2011b, Chapter 1.2.4). The most common quantitative tool for value for money assessment of a PPP project is derived from the approach originally used in the United Kingdom's PFI program in the early 1990s as described in Leigland and Shugart's Gridlines article on the PSC (Leigland and Shugart 2006). It involves comparing the fiscal cost of a PPP delivery option with that of a conventional public delivery option—not a single conventional option, but a range of infrastructure options as noted in the 2011 Treasury Guidance on Valuing Infrastructure Spend (UK 2015a). NAO evidence presented in the House of Commons 2014 report (UK 2014a) discusses several shortcomings in the identification of PSCs. The focus of the Fiscal Cost approach to value for money analysis is the construction of a PSC—the cost to government of implementing the project through traditional public procurement. Calculating the PSC can be complicated, as several adjustments are needed to ensure a fair comparison. How the Public Sector Comparator is calculated, highlights some methodological debates. This type of PSC can be used at two stages of the procurement process, as described in the OECD book's chapter on the economics of PPPs (OECD 2008a, 71–72). These are: Despite the appealing logic of the concept, there have been many criticisms of the usefulness of the PSC and fiscal cost comparison approach in countries where it has been used frequently, such as the United Kingdom and Australia. A United Kingdom House of Lords' review of the PPP program (NAO 2013a), for example, argued that shortage of relevant data and methodological issues limit the value of the PSC. The government's response to the review agrees that the PSC provides only a partial picture, and highlights that its use is balanced with qualitative analysis, as described above. Leigland and Shugart's Gridlines article on the PSC (Leigland and Shugart 2006, 2–3) summarizes these criticisms, which include the inevitable inaccuracy of estimates over a long-term project, lack of consensus on methodology, and so the possibility of manipulation to reach the desired conclusion. Grimsey and Lewis (Grimsey and Lewis 2005, 362–371) describe some of these criticisms in more detail. Given these challenges, Leigland and Shugart's Gridlines article (Leigland and Shugart 2006, 3–4) also discusses whether and how the PSC approach could make sense in a developing country context. Calculating a PSC can be complex. The starting point is typically the best estimate of the capital cost and lifetime operations and maintenance cost of implementing the project under public procurement. This is typically adjusted, to enable a fair comparison between the PSC and the PPP. The Infrastructure Australia guidance note on PSC (AU 2011b, Section 2.3) describes two types of adjustment: There are also differences in the timing of payments between the PPP option—where payments are often spread over time—and traditional procurement, where the government must meet construction costs upfront. The streams of payments are usually converted into net present values, to give a single value for comparison. This requires defining the appropriate discount rate to apply to future cash flows in both the PPP and PSC models. The following provide further descriptions and examples of how the PSC is used and calculated in different countries: Methodological differences and challenges Although the PSC has been widely used, the methodology differs between countries, and there is ongoing debate on several methodological points. For example, Shugart’s article on the PSC (Shugart 2006) highlights two related issues: which is the appropriate discount rate to use when calculating present values, and how the cost of risk should be considered. Grimsey and Lewis (Grimsey and Lewis 2004) and Gray, Hall and Pollard (Gray et al. 2010) both focus on the choice of discount rate, and its relationship with risk allocation under PPP and traditional procurement. In IFC’s report on lessons learned (IFC 2010, 7-13), José Luis Flores presents a concrete case of “value for money” assessment. Some countries in Latin America, such as Colombia and Peru, have developed guidelines for implementing the PSC methodology. However, due to lack of capacity and or trustworthy information to implement such a complex methodology, none of these countries have implemented the full methodology in practice. The World Bank report on Value for Money assessment practices (WB 2013a, 23–28) reviews methodological evolution and practices in several governments with significant PPP experience, including the United Kingdom, France, India, Chile, the U.S. state of Virginia, and British Columbia, Canada. One of the criticisms sometimes leveled at the PSC is that it focuses solely on the financial cost to government of PPP or traditional procurement. A more comprehensive approach would also consider the differences in expected benefits, and compare the net economic benefit under PPP or under public procurement. On the other hand, as Grimsey and Lewis note (Grimsey and Lewis 2004, 353), this adds further complexity to the value for money analysis over the PSC approach, and could risk making the results even more subjective. For example, the EPEC's note on non-financial benefits of PPP (EPEC 2011c) suggests how some of the benefits of PPP—as described in Infrastructure Challenges and How PPPs Can Help—could be quantified, and added to a more typical PSC analysis. Few countries have introduced this kind of analysis in practice. New Zealand's new PPP program is an exception. Cost-benefit analysis is the main tool for assessing procurement options. New Zealand's PPP guidance material (NZ 2016, 6–12) asks practitioners to identify the possible benefits of PPP over traditional public procurement and where possible to assign dollar values to each benefit. In many developing countries' PPP programs, the aim is not just to reduce cost, but to transform service delivery. For example, governments hope that roads will be better maintained, thus delivering additional trade and economic benefits. These changes in service levels and quality cannot be captured by comparing fiscal costs of PPP and public procurement. Where these expected benefits are deemed important, and quantitative value for money analysis is desired, economic cost-benefit analysis may be the better approach.
Qualitative value for money assessment
Public Sector Comparator—comparing fiscal cost
Economic cost-benefit comparison of PPP and public procurement
Find in pdf at PPP Reference Guide - PPP Cycle or visit the PPP Online Reference Guide section to find out more.
Related Content
INTRODUCTION
Page Specific DisclaimerVisit the PPP Online Reference Guide section to find out more.
PPP BASICS: WHAT AND WHY
Page Specific DisclaimerVisit the PPP Online Reference Guide section to find out more.
Featured Section LinksESTABLISHING THE PPP FRAMEWORK
Page Specific DisclaimerVisit the PPP Online Reference Guide section to find out more.
PPP CYCLE
Page Specific DisclaimerVisit the PPP Online Reference Guide section to find out more.
Identifying PPP Projects
Type of ResourceAppraising Potential PPP Projects
Type of ResourceStructuring PPP Projects
Type of ResourceDesigning PPP Contracts
Type of ResourceManaging PPP Transactions
Type of ResourceManaging PPP Contracts
Type of ResourceDealing with Unsolicited Proposals
Type of ResourceKey References - PPP Cycle
Type of Resource
Additional Resources
Procurement Processes and Bidding Documents
Type of ResourceStandardized Agreements, Bidding Documents and Guidance Manuals
Type of Resource