Standardisation of PFI Contracts (SoPC) Version 4 (March 2007)

On Chapters 11 - 20: The Contractor will base its costings on a forecast capital replacement programme of plant, machinery, equipment, fixtures, fittings and furniture designed to maintain the building environment at the specified output standards. The Contractor will also consider the means of funding this expenditure throughout the life of the Project. The risk associated with assessing what will need replacing, when and how much this will cost, is one that the Contractor should take and therefore the Authority should not attempt to be prescriptive in this respect.

Standard Form Public Private Partnership (PPP) Project Agreement

The document was prepared for a facilities management contract and will need to be adjusted for a full operations projects.

Related information: 

Standardized Agreements, Bidding Documents and Guidance Manuals. 

Tracking Number:

New Zealand_Standard Form PPP Agreement_framework_EN.pdf

New Zealand_Standard Form PPP Agreement_EN.pdf

New Zealand_Standard Form PPP Agreement_schedules_EN.pdf

Green Book - Model Concession Agreement for Brownfield Hospital

Model concession agreement for a brownfield hospital (secondary / tertiary care) on design, build, develop, upgrade, finance, operate and transfer (DBDFOT) basis and  services (including supply of equipment and staff) to concessionaire's own private patients as well as a minimum of public health funded patients. Developed for use by states for health care provision

Authority is the relevant state.

Authority to provide land for facility.

[Authority will pay a grant to reduce financing costs] Concessionaire to pay a concession fee