Benchmarking Period Checklist and Sample Wording

Photo Credit: Image by noelsch from Pixabay
In infrastructure projects involving existing assets or utilities, the data provided prior to commencement of the contract is often inaccurate, resulting in inaccuracies in the assumptions for financial modelling and performance standards.
This page suggests a solution and provides sample wording for an initial benchmarking period at the beginning of a contract.
You can also download a word version of the Benchmarking Period Checklist. A benchmarking period enables the operator to establish, with the participation of the awarding authority, the base case for performance and asset condition during a preliminary phase of the project. The disadvantages are that: - The alternative solution is for the base data to be established prior to contract commencement by consultants or other third party; however, it is often difficult to establish the performance parameters where day to day management is not being overseen as it is difficult to verify data such as billing through isolated verification. Obligations of Operator during the Benchmarking Period During the Benchmarking Period, the Operator shall use reasonable endeavors to perform the [Outsourced Activities] from the Effective Date to standards not less than those achieved by the Owner as at the date of the Contract. The Operator will only be liable during this period for loss or damage directly caused by negligence, wilful default or fraud of the Operator. The Operator will not be liable for any Liquidated Damages during the Benchmarking Period. [During the Benchmarking Period the Operator will also, with the assistance and co-operation of the Owner, perform the following activities: Benchmarking Activities At the beginning of the Benchmarking Period the Operator shall install and/or recalibrate the [input and output meters][electricity meters] and all other meters [Meters] that the parties agree are necessary to calibrate the system as provided within the [Agreed Capital Investment Program] and the Parties will calibrate all the Meters jointly. The Parties will then jointly take meter readings from all relevant Meters over a minimum period of [six months]. During the Benchmarking Period all of the parameters of operation such as water quantities pumped, water quantities received, expenditure incurred, electricity consumed, chemicals consumed, maintenance costs, etc. will be benchmarked against the Base Charge Data. At the end of the Benchmarking Period, if and to the extent necessary, the variable rates will be adjusted in line with actual expenditure and volumes of water pumped to take into account the Base Charge Data, as has been verified during the Benchmarking Period. During the Benchmarking Period the Operator in consultation with the Owner will also take monthly samples and monitor performance in order to collate the Base Performance Data against the criteria set out in Schedule [ ] (Performance Indicators). Conclusions of benchmarking At the end of the Benchmarking Period the Operator will propose: The Performance Standards will be based on the Performance Indicators. The Performance Standards and the Liquidated Damages will be set at levels which are reasonable in the context of the Base Performance Data, the level of investment contemplated by the Contract and the other terms of the Contract. If the parties cannot agree these Performance Standards or Liquidated Damages within [30] days of the response then they shall refer the matter to Arbitration. Adjustment to Specifications The Specifications will be adjusted, to the extent appropriate, in accordance with the Base Performance Data. Definitions: 1. It may be possible to set the levels of liquidated damages – or at least estimate them – prior to contract signature and only amend them if there are material levels in the actual performance levels.General
Key issues to consider in relation to the benchmarking period
Sample Wording
Related Content
Tools
KeywordsBenchmarking
KeywordsPPP Sector Specific Checklists
Type of ResourceChecklists for Key Legal/ Drafting Issues in PPPs and sample clauses
Type of ResourceToolkits for Public-Private Partnerships
Sample PPP Clauses
Sample Terms of Reference (TORs) for PPP Advisors
PPP Reference Guide
Welcome to ChatPPP!
KeywordsBanner Notice
Watch this space. This section will evolve with new resources to be added. Enjoy this new experience as we rely on technology more than ever to connect and collaborate. Thank you for being part of the Community. Registration is required.
Additional Resources
PPP Arrangements/Types of PPP Agreements
Page Specific Disclaimer*Note: Although the key features of each category are summarized, there is overlap between the categories and the name given to a particular agreement may not reflect this classic categorization. Care should also be taken to identify whether a specific classification is enshrined in the laws of the host country, as in the case of many civil law jurisdictions where there are strict definitions of "concessions" and "affermages". The sample agreements included in this section are not the full range of agreements associated with infrastructure projects. They agreements are NOT intended to be used as "models". Legal advice should be sought in the preparation and drafting of an agreement to ensure that it is appropriate and workable in the circumstances of a particular project, sector and country. Find Terms and Conditions of this website here.
Select WBG PPP Toolkits
Featured Section LinksPPP Reference Guide