Force Majeure - Checklist and Sample Wording

Certain events, beyond the control of the PPP parties, may inhibit the parties from fulfilling their duties and obligations under the project agreements.

To avoid the resultant breach of contract, parties may prefer to excuse contractual obligations to the extent that they have been so inhibited.

Different legal systems have developed different theories in response to this need, including the doctrines of impossibility and frustration in England and the United States and force majeure in France. Under French law force majeure is an event that is unforeseeable, unavoidable and external that makes execution impossible.

In order to avoid the uncertainties and delays involved in relying on the applicable law, parties to contracts often prefer to provide for a specific regime for force majeure, along with a definition of which events shall qualify for special treatment.

The term force majeure used in drafting project documents comes originally from the Code Napoléon of France, but should not be confused with the French doctrine. Generally, force majeure means what the contract says it mea

Disclaimer: The resources on this site is usually managed by third party websites. The World Bank does not take responsibility for the accuracy, completeness, or quality of the information provided, or for any broken links or moved resources. Any changes in the underlying website or link may result in changes to the analysis and recommendations set forth on the Public-Private Partnership Resource Center. The inclusion of documents on this website should not be construed as either a commitment to provide financing or an endorsement by the World Bank of the quality of the document or project. If you have any comments on any of the links provided on the Public-Private Partnership Resource Center, please get in touch here