Force majeure/act of god

Library Library
Termination and Force Majeure Provisions in PPP Contracts

Termination and Force Majeure Provisions in PPP Contracts - Review of current European practice and guidance, by the European PPP Expertise Centre (EPEC) and Allen & Overy, March 2013. 

article Article
Dealing with Change

Over the life of a typical PPP contract—10 to 30 years—developments will occur that could not have been predicted when the contract was signed. It is also likely that the parties will dispute…

article Article
Sample Force Majeure Clauses

Find a summary of termination and force majeure provisions used in PPP projects in Europe in EPEC guidance - Termination and Force Majeure Provisions in PPP Contracts - Europe.Example 1 -…

article Article
Force Majeure Checklist

What is force majeure?Certain events, beyond the control of the parties, may inhibit the parties from fulfilling their duties and obligations under the project agreements. To avoid the resultant…