The feasibility study for the Burkina Faso's Hybridization of Banfora Gold Mine.

A previous study by Ernst & Young (Dec. 2018) showed the relevance of developing a solar PV power plant near the mine to meet more than 50% of its needs. The implementation of the project is proposed in 3 progressive phases:
1. HFO plant only: which is currently in service to supply the mine (reference cost)
2. HFO plant + Solar/battery plant: hybridization of the existing plant in isolated mode, possibly connected to the existing MV network
3. HFO power plant + Solar/battery power plant + HTB network: ultimate connection of the hybrid HFO/PV/battery power plant to the HTB network (e.g. 132kV). It should be noted that the existing HTB network (225kV) is more than 80km from the mine and that an extension to the mine is conditioned by the uncertain construction of an HTB substation near Banfora (no funding yet).

Disclaimer: The resources on this site is usually managed by third party websites. The World Bank does not take responsibility for the accuracy, completeness, or quality of the information provided, or for any broken links or moved resources. Any changes in the underlying website or link may result in changes to the analysis and recommendations set forth on the Public-Private Partnership Resource Center. The inclusion of documents on this website should not be construed as either a commitment to provide financing or an endorsement by the World Bank of the quality of the document or project. If you have any comments on any of the links provided on the Public-Private Partnership Resource Center, please get in touch here